Garbage recycling centrum presentation

2012-03-25_Präsentation+Baustofftrennung

Louis Palmer presentation of the task:

RECYCTOWER

ZÜRIFÄSCHT RECYCLING FUN PROJECTS

 generally there are these conditions:

Tower more than 9 meters (the higher the better)
truck  2 x 2 x 8 m
150 000 bottles
good looking
build the tower in 1, 5 days
the tower must be built from elements, that school kids are able to construct, we have 240 classes to do this
we have 1 crane
on beton platform:
where: on the riverside of Limmat, Landiwiese